Key California lien deadlines
Lien rights in California are strict about timing. Missing a date can mean losing the right to lien the property at all. These are the general windows under the California Civil Code:
| Step | Who | General deadline | Civil Code |
|---|---|---|---|
| Preliminary notice | Subcontractors, suppliers, equipment lessors | Within 20 days of first furnishing labor or materials | § 8204 |
| Record lien | Direct contractor | After completion, and within 90 days of completion, or 60 days after a recorded notice of completion or cessation | § 8412 |
| Record lien | Subcontractors and suppliers | After completion, and within 90 days of completion, or 30 days after a recorded notice of completion or cessation | § 8414 |
| Enforce lien | Anyone who recorded a lien | File a foreclosure lawsuit within 90 days after recording | § 8460 |
General information only, not legal advice. Your dates depend on your contract and the project, so confirm them with a lien service or construction attorney.
How lien consulting works
- Deadline tracking: each job's first furnishing date, completion, and any recorded notices, with lien windows on a calendar.
- Records: contract, change orders, invoices, and payment history organized to support the claim amount.
- Filing through a licensed service: the preliminary notice or lien is prepared and recorded by a third-party lien service, with TR Holmes coordinating the information.
- Release tracking: conditional and unconditional lien releases matched to payments received.
Collections support
Most unpaid invoices are fixed long before a lien: clear invoices, steady follow-up, and records that show exactly what's owed.
- Accounts receivable aging reviewed every month
- Payment reminders and statements sent on a schedule
- Demand letters drafted for your signature
- Documentation packaged for an attorney or collection agency when an account needs escalating
Questions
Do you file mechanics liens?
TR Holmes consults on California mechanics liens: tracking deadlines, gathering contract and payment records, and preparing the information needed. The lien itself is prepared and recorded through a licensed third-party lien service.
What is a California preliminary notice?
A preliminary notice (often called a 20-day notice) tells the owner, direct contractor, and lender that you are supplying labor or materials to a project. Subcontractors and suppliers generally must serve it to preserve lien rights, and it should go out within 20 days of first furnishing work.
How long do I have to record a mechanics lien in California?
It depends on your role and whether a notice of completion or cessation is recorded. A direct contractor generally has 90 days after completion, or 60 days after a recorded notice. Subcontractors and suppliers generally have 90 days after completion, or 30 days after a recorded notice. Check your specific dates with a lien service or attorney.
Is this legal advice?
No. TR Holmes is not a law firm. The information here is general, and complex disputes should go to a construction attorney.
Get your books caught up before the next job starts.
Call, email, or send a short note about your business. You'll hear back within one business day.